We will continue to add to and update this throughout the 2 year initiative.
You can submit questions here , email council@ctrockford.org , or in person to Kevin Jensen.
We will post answers to your emails in as timely a manner as possible.
Please continue to check here for those updates. If you'd like to step into the initiative you can scroll down to our commitment card.
ANCHORED FAQ
Thanks for checking out our FAQ's page. Anchored is Christ the Rock's 2 year initiative for our gymnasium and sanctuary renovation. On this page you will find questions that have been asked by members of the congregation and their answers.
FAQ
Click on the questions below to see the dropdown for the answer.
-
Once the motion has been approved we will submit our application. Between underwriting, approval and closing the whole process will take anywhere from 20-30 days. Very much like a home closing.
-
LCEF asks that ALL properties be put forward as collateral for the loan. For Christ the Rock, this would be Church, Parsonage, parking and garage and the extra parcel of land.
-
10-12 weeks
-
6-8 weeks
-
Yes, most of it can overlap but Cord may need the construction documents to finalize some of the bidding for work
-
16 weeks but they would like a 2 week buffer for a total of 18 weeks.
-
Yes, we need full final approval, but this can take place during the 10-12 weeks of the construction drawings. It typically takes 30-60 days.
-
As quick as 14 weeks but could be as much as 18 weeks.
Giving and Support
How can i support Anchored